Construction Updates

ELEMENTARY UPDATES

 
Elementary School Roofing  (09.30.2025)
 
 
 

Roof work is expected to be complete by the end of October 2025.

elem-roof1.png
elem-roof2.png

AUTO MECHANICS FACILITY

 
 

MHS Auto Mechanics Facility (09.30.2025)

 

Water lines being installed.  Insulation panels are on a 16-week back order.

autoshop-1.png

MCGREGOR HIGH SCHOOL 

MHS Parking Lot and Gym (09.30.2025)
 
 

Parking lot and gym construction are underway.

 
hsparking-gym-2.png

JUNIOR HIGH SCHOOL

 
Front Entrance (09.30.2025)
 

Front entrance of campus is being prepped.

 
jh-frontentry-3.png
jh-frontentry-1.png
jh-frontentry-2.png
Junior High Classrooms (09.30.2025)
 
 
 

Classrooms should have sheetrock installed during October 2025.

jh-classrooms-1.png
jh-classrooms-2.png
Junior Gym (09.30.2025)

Exterior gymnasium walls are going up.

 
jh-gymwalls-2.png

MISD AGRICULTURAL FACILITY  

Agricultural Facility (09.30.2025)
 
 

Construction is in the final phase.

 
agbarn-1.png
agbarn-4.png